Project
Refurbishment and recommissioning of major distribution hubs

Project
Transforming dormant sites into operational hubs
NIRAS was engaged to manage the transformation of two large distribution centres taken over by a multinational retailer. The project required full dilapidation, refurbishment, and installation of bespoke storage systems - all while preparing for partial operational go-live before project completion.
With a strong focus on safety and sequencing, NIRAS deployed its accredited OHSAS18001 site management system. We coordinated over 20 contractors, delivering:
Comprehensive pre-site onboarding and competency checks
Round-the-clock site supervision by dedicated HSE managers
Robust sequencing to support safe installation at height
The complexity of the project demanded precision planning and unwavering oversight, particularly as the client ramped up operations before final handover.
The 64-week programme delivered significant operational benefits and a safe working environment throughout:
290,000+ manhours worked
2,800+ health and safety inspections
2,200+ site inductions
1,200+ permits issued
350+ Toolbox Talks delivered
NIRAS brought structure, safety, and certainty to a high-risk, high-volume programme - enabling a smooth transition from dormant infrastructure to live logistics operations.